How can a project manager ensure that estimates are accurate and how bad estimates can lead to good projects failing
Estimating is a critical part of
project planning, involving a quantitative estimate of project costs, resources
or duration. Typically, a project estimate shows the client: Tasks –
What’s going to be done, Resources – By who, Rate – At
what billing rate, in what currency, with how much tax, Duration –
For how many hours or days, and + any mark-up and 3rd party
costs (such as hosting, photography, travel or subsistence).
Accurate Estimates
1. Designate a Lead Estimator
2.
Encourage Bottom-Up Estimating
3.
Gather Detailed Requirements
4.
Determine Pessimistic, Best Guess, and Optimistic Estimates
5.
Encourage Communication among Project Members
6. Include Finance and Legal Staff
The project manager can ensure that
his estimates are correct by beginning with estimating the time needed for each
task rather than for the project as a whole. The level of detail they need to
go into depends on the circumstances. For example, you may only need a rough
outline of time estimates for future project phases, but you'll probably need
detailed estimates for the phase ahead. They should list all of the
assumptions, exclusions and constraints that are relevant; and note any data
sources that they rely on. This will help when estimates are questioned, and
will also help identify any risk areas if circumstances change. Assuming that resources
will only be productive for 80 percent of the time.
Building in time for unexpected
events such as sickness, supply problems, equipment failure, accidents and
emergencies, problem solving, and meetings. If some people are only working
"part-time" on a project, it’s important to bear in mind that they
may lose time as they switch between their various roles. Remember that people
are often overly optimistic, and may significantly underestimate the amount of
time that it will take for them to complete tasks.
Bad Estimates
Estimation is at the heart of
most project disciplines, and project cost and time overruns can often be
traced back to inaccurate estimates.
Project estimates go wrong due to:
1. False
analogies
2. False
precision
3. Estimation
by decree
4. Subjectivity
5. Coordination
neglect
6. Too coarse
grained
7. The one size
fits all approach
Inexperienced
estimators tend to be overly optimistic and assume that everything will go
right. More experienced estimators tend to assume everything will go wrong and
so pad their estimates accordingly. But, in the planning process, this padding can become cumulative (as
above) resulting in poor overall estimates. And, as the estimates drive the
costs, this can unnecessarily increase the cost of the project. Poor estimating is also encouraged by a project's culture. Senior management conveniently forgets the meaning of the word
"estimates" and assumes they should be accurate, "If you know
what you're doing." But management ask for too much accuracy too soon.
When
"final" estimates are required too early in the project delivery
process (before the requirements, let alone the solution have been defined),
the level of reliable information required for estimating is too low for
accurate.

Comments
Post a Comment